Low-Energy Bottle Washing Machine
Residual draining machine
Residual draining machine
Residual draining machine

1.000 to 8.000 bottles / hour

Working Method

Single-ended machine using the combined soak- and spray method. Bottle cells mounted on an endless chain pass through the following zones:

Pre-sprinkling, discharge of remains, pre-spraying, caustic soaking, caustic flushing in two positions to remove labels, hot caustic spaying with high volume and low pressure.

Cool down area consisting of: Caustic-II zone, warm-water spray zone, cold-water spray zone and fresh-water spray zone.

Extensive drip zones result in low alkalinity in the water spray zones. The cascade principle, where the flow of water inside the machine is opposite to the transport direction of the bottles, results in an automatic regulation of temperature in all treatment zones.

» Video PAC Residual draining machines

Residual draining machine

Legend

1 Bottle infeed table
2
Bottle feeding
3
Bottle outfeeding
4
Bottle outlet conveyor
5
Main drive motor
8
Caustic-II spraying
9
Caustic-soaking I
11
Caustic showering
12
Hot caustic spraying
13
Residual caustic deflation
14 Warm-water spraying I
16
Cold-water spraying I
17
Water pre-spraying zone
18
Clock- and interval spraying zone
19
Pre-sprinkling
22
Residual water deflation
25
Drainage for service-water
26
Discharge of remains
27
Dosage for soaking
28 Heat recovery
30
Label discharger
31
Shards channel
32
Switchboard
33
Lights
34
Switchboard ventilation
35
Overflow
36
Heat exchanger
37
Vapor exhaust
38
Isolation